Automotive moulds, designed and built in our own tool room
Premier Plasmotec designs and builds 200+ moulds a year in its own tool room, for the parts we mould for India’s car, scooter and motorcycle makers. A new mould typically reaches first trial in 45 to 60 days.
Send us your part data and annual volume.
Email info@plasmotec.com
At a glance
| Item | Detail |
|---|---|
| Output | 200+ moulds a year |
| Lead time | Typically 45 to 60 days to first trial |
| Team | 10 design engineers, a 12-person project team and a 40-person tool room |
| Design | Unigraphics NX, with mould-flow simulation on every new design |
| Machining | 5 vertical milling centres, 5 EDM machines, 3 surface grinders, 2 radial drills, 2 tapping machines |
| Fitting | 2 die-spotting machines |
| Tool room | Faridabad, Haryana, in-house since 2002 |
One mould, one cycle
The cavity half and core half close, the part forms between them, the mould opens and the ejector pins push the part out. Our tool room designs and builds these moulds for the parts we make.
- 200+
- moulds a year
- 45 to 60
- days to first trial, typically
- Since 2002
- our own tool room
From your A-surface to a proven mould
On our newest programmes, the mould starts with a part we designed. You give us the A-surface, and our 10 design engineers design the B-surface to your guidelines. Mould-flow simulation checks every new design for sink marks, warpage, weld lines and short fills before you approve it.
The mould is then designed from that same model, so a wall thickness or gate position that would cause trouble in the tool gets fixed in the part design, not after the first trial. We have taken three models from A-surface to mass production this way, for a passenger vehicle maker and a two-wheeler maker.
How we build a mould
- Design for manufacture (DFM) report and mould concept, for your approval: we review the part’s tolerances, add draft angles where the part data has none, flag aesthetic risks such as warpage, and propose the cavity count, gate and runner layout, cooling and ejection, all before any steel is cut.
- Mould-flow simulation, then mould design in Unigraphics NX.
- Machining on our vertical milling centres and EDM machines.
- Fitting on the die-spotting machines, and inspection against the design.
- First trial on a production press, run by the toolmakers with the team that will mould the part. Samples are measured, and the mould is corrected until the part matches the drawing.
- Hand-over to production and PPAP submission.
Typically 45 to 60 days from start to first trial, depending on the mould’s size and complexity.
Soft tools for prototypes
Before committing to production steel, we can build a soft tool in C45 steel to mould prototype parts for fit and function trials. It takes about as long as a production mould but costs less, so you test real moulded parts, not printed models, before paying for the production tool.
Why Premier Plasmotec
- Our own tool room since 2002, building 200+ moulds a year
- One team answers for the part, from A-surface to series production
- Mould-flow simulation on every new design
- 410 injection moulding machines, up to 1,600 tonnes, to run the moulds we build
Questions buyers ask
How long does a new mould take? Typically 45 to 60 days to first trial, depending on size and complexity.
Can you take over an existing mould from another supplier? Yes. We check the mould’s condition when it arrives, and make any engineering change it needs in our own tool room.
Which mould steels do you use? P20, high-hard P20, H13 and Stavax. We choose the steel for each mould by the number of shots it must run and what the part needs.
Do you build hot-runner moulds? Yes.
Who maintains the mould during production? We do, for every mould that runs in our plants.
Talk to us